Tours
Schedule a tour at the Dominion website today!
Schedule
Dominion Senior Living of Northfield Construction Update
January 2020
Posted 01.14.20
Current Status
- Installing Masonry on Wing A and B
- MEPFP rough ins on going all wings
- Installing drywall in Wings C and B
4-Week Look Ahead
- Complete masonry veneer
- Continue electric & HVAC installations all wings
- Continue drywall in all wings
- Prime walls in wing C
November 2019
Posted 11.15.19
Current Status
- Installing roof sheeting in Wing A
- Installing Masonry on Wing C and B
- MEPFP rough ins on going all wings
- Installing fence along berm
- Installing drywall in Wing C
4-Week Look Ahead
- Complete framing Wing A
- Continue electric & HVAC installations all wings
- Roofing and windows installed in Wing A
- Complete fence along berm
September 2019
Posted 09.23.19
Current Status
- Framing complete in Wing C
- Framing nearly complete on Wing B
- Floor slab in Wing A is complete
- Roofing installed in Wing C
4-Week Look Ahead
- Begin Framing Wing A
- Continue electric & HVAC installations Wing C
- Roofing in Wing B
July 2019
Posted 07.25.19
Current Status
- CMU foundation walls complete
- prepping and pouring concrete floor slabs
- wall framing has begun
- constructing masonry elevator shaft
4-Week Look Ahead
- complete concrete slabs
- install plumbing underground
- install underground electric
- complete CMU at elevator shaft
- complete framing of C Wing
- begin framing delivery for B Wing
Current Status
- Concrete foundation footings complete
- 85% CMU foundation walls complete
4-Week Look Ahead
- Complete CMU foundation walls
- Install plumbing underground
- Begin floor slab pours
- Install temporary electric
Week of January 28th, 2019
Posted 01.29.19
As of January 21st, phase one of the Dominion Senior Living Center is officially opened and accepting residents. A Grand Opening event will be held on February 28th to tour the new facility.
Week of October 1st, 2018
Posted 11.19.18
2-Week Look ahead:
- Complete Exterior Painting
- Complete Exterior Fencing
- Landscaping is Complete
- Complete Flooring
- Complete Kitchen
Upcoming Milestones:
- 12/5 – Granite installation
- 12/10 – Furniture Install
- 12/17 – Building Completion
Week of August 27th, 2018
Posted 08.30.18
2-Week Look ahead:
- Continue Exterior Painting
- Gutters Begin
- Interior drywall finishes
- Door and Trim Installation continues
- All rough in inspections have been passed
Upcoming Milestones:
- 10/1 - Exterior Complete
- 10/1 - Flooring begins
- 10/15 - Landscaping and Courtyards
- 11/1 - Certificate of Occupancy

Exteriors

Memory Care Unit Interior